{# ----------------------------------------------------------------------------- I. CITY HEADER ----------------------------------------------------------------------------- #}
SHEET 01 / 09 · Header

Dossier · Los Angeles County

Building an ADU in Long Beach.

33°46′ N · 118°11′ W

Long Beach is the faster-moving cousin to Los Angeles: similar rules, lighter queue, and a planning department that publishes checklists. The city has actively encouraged garage conversions as a way to add housing without changing neighborhood character.

{# ----------------------------------------------------------------------------- II. THE NUMBERS — at-a-glance stat band, city-specific ----------------------------------------------------------------------------- #}
SHEET 02 / 09 · The numbers

The numbers, at a glance.

Four data points to anchor every conversation you'll have with a contractor, architect, or permit expediter in Long Beach.

Typical permit fee $4,200

City permit + plan-check fee for a mid-size ADU. Excludes school & impact fees.

-$2k vs LA-area median
Permit timeline 8–14 wks

From a complete application to permit issuance. Plan-check rounds extend this.

Long Beach planning portal · 2026-05
Rent (1-bed ADU) $1,600 – $2,800

Long-term rental range, market rate, 2026 estimates.

Source · 2026 Zillow / Apartment List blends
Median lot 5200 sf

Typical single-family parcel — your lot determines what's physically possible.

Source · LA County Assessor blends
{# ----------------------------------------------------------------------------- III. NOTABLE LOCAL RULE — the unique data point ----------------------------------------------------------------------------- #}
SHEET 03 / 09 · Local rule

The local rule that matters.

RULE · LONG BEACH

Long Beach allows ADUs in any single- or multi-family zone and does not require a covered parking replacement when a garage is converted — a meaningful cost-saver versus older interpretations.

Every California city must comply with the statewide ADU framework, but each one has a local quirk — a program, an overlay, or an interpretation — that changes the math. This is the one to read first for Long Beach.

{# ----------------------------------------------------------------------------- IV. PERMIT & FEE DETAIL ----------------------------------------------------------------------------- #}
SHEET 04 / 09 · Permits & fees

Permit fees & impact fees, decoded.

Your city's permit fee is the visible cost. Impact fees and utility connection fees are where projects get expensive without warning — read this carefully.

Typical permit + plan-check fee
$4,200
Processing window
8–14 weeks (application to issuance)
City planning portal
Open in new tab →

Impact fees

Long Beach charges park and library impact fees on ADUs over 750 sqft. School fees go to LBUSD at the state-mandated rate. Most garage conversions skip impact fees entirely because they don't add floor area beyond the existing footprint.

{# ----------------------------------------------------------------------------- V. COST RANGES — pre-multiplied for THIS city across all 3 ADU types ----------------------------------------------------------------------------- #}
SHEET 05 / 09 · Cost ranges

What it costs in Long Beach.

Standard-finish, default-size totals for each ADU type — including Long Beach's permit fee, typical soft costs, utility hookups, and a 10% contingency. Property value uplift assumes a los angeles county lot baseline.

Detached new construction 800 sqft · Standard finish
$346k$457k
  • Build & finishes $288k–$368k
  • Permit & plan check $4k
  • Soft costs $14k–$29k
  • Utilities $8k–$14k
  • Contingency (10%) $31k–$41k

Property value uplift +$250k–$350k

Attached new construction 600 sqft · Standard finish
$228k$312k
  • Build & finishes $186k–$246k
  • Permit & plan check $4k
  • Soft costs $9k–$19k
  • Utilities $8k–$14k
  • Contingency (10%) $20k–$28k

Property value uplift +$250k–$350k

Garage conversion 400 sqft · Standard finish
$110k$157k
  • Build & finishes $84k–$116k
  • Permit & plan check $4k
  • Soft costs $4k–$9k
  • Utilities $8k–$14k
  • Contingency (10%) $10k–$14k

Property value uplift +$250k–$350k

Numbers reflect 2026 LA-area build costs at standard finishes. Luxe finishes add roughly 30–35%; basic finishes subtract 15%. The Phase-4 estimator will let you set every input.

{# ----------------------------------------------------------------------------- VI. SIX-PHASE TIMELINE — universal but with this city's window highlighted ----------------------------------------------------------------------------- #}
SHEET 06 / 09 · Timeline

The six phases for Long Beach.

Universal sequence, with Long Beach's 8–14-week plan-check window slotted in. Total project clock typically runs 9–14 months for this city.

  1. 01

    Feasibility & design intent

    Walk the lot. Confirm zoning, setbacks, easements, hillside or coastal overlays. Pick a rough size and ADU type.

    3–6 wks
  2. 02

    Working drawings

    Architect produces permit-ready plans. Soils report and survey ordered if the lot requires them.

    4–8 wks
  3. 03

    Plan check & corrections — at Long Beach planning

    Submit to Long Beach. State law caps the first review at 60 days; most projects go through two or three rounds of corrections.

    8–14 wks
  4. 04

    Permit issuance & pre-construction

    Pay fees. Pull the permit. Line up the contractor's crew and financing draw schedule.

    1–2 wks
  5. 05

    Construction

    Site prep, foundation, framing, MEP rough-in, drywall, finishes. Inspections happen at each gate.

    4–8 mos
  6. 06

    Final inspection & Certificate of Occupancy

    Final building, electrical, plumbing, and (if applicable) fire inspections. Once the C of O is issued, you can legally rent it.

    2–4 wks
{# ----------------------------------------------------------------------------- VII. STATE LAWS — every CA city has to follow these ----------------------------------------------------------------------------- #}
SHEET 07 / 09 · State law

State law Long Beach has to follow.

These statewide statutes override any local rule that conflicts — including in Long Beach. Read these alongside the Long Beach planning portal.

SB 1211 (2024) Eff. Jan 1, 2025

Up to eight detached ADUs on multifamily lots, minimum 18-foot height

Owners of multifamily parcels (duplex and up) can now build up to eight detached ADUs by-right, capped at the number of existing primary units. The bill also raised the statewide minimum ADU height from 16 to 18 feet for parcels near transit, giving room for a usable second story.

Owners of duplex, triplex, and larger multifamily parcels.
AB 1033 (2023) Eff. Jan 1, 2024

ADUs can be sold separately from the primary home (local opt-in)

Cities may now adopt an ordinance allowing ADUs to be sold as condominiums separately from the primary residence. Adoption is permissive — only a handful of California cities have opted in so far, but it's a meaningful exit-path option to track.

Single-family homeowners in cities that have opted in.
AB 976 (2023) Eff. Jan 1, 2024

Owner-occupancy requirements made permanent

Cities cannot require the owner to live on-site as a condition of permitting a new ADU. This makes the ADU a much more flexible long-term financial asset — you can move, keep the property, and rent both units.

Anyone building an ADU and weighing whether to keep the home long-term.
AB 2533 (2024) Eff. Jan 1, 2025

Pre-existing unpermitted ADUs — clearer path to legalization

Reduces barriers to permitting unpermitted ADUs built before January 2020. Cities can no longer require correction to current code for items that were code-compliant at the original build date, with limited health-and-safety exceptions.

Owners with informal ADUs, conversions, or backyard cottages.
AB 2221 + SB 897 (2022) Eff. Jan 1, 2023

Streamlined ministerial approval for detached ADUs

Detached ADUs up to 800 sqft, 16 feet tall, with 4-foot setbacks are approved ministerially — no discretionary review, no design review, no public hearing. Cities must act within 60 days of a complete application.

Anyone building a code-minimum detached ADU.
{# ----------------------------------------------------------------------------- VIII. FAQ ----------------------------------------------------------------------------- #}
SHEET 08 / 09 · FAQ

Questions for Long Beach homeowners.

The questions Long Beach homeowners actually ask, drawn from real conversations with architects and permit consultants.

Do I need to live on-site to build or rent an ADU?
No. AB 976 made owner-occupancy requirements permanently illegal in California. You can build an ADU, rent both the primary and the ADU, and live elsewhere — though local short-term-rental rules (Airbnb, etc.) still apply.
Will building an ADU re-assess my property taxes?
Only the new ADU portion is re-assessed at current market value. Your existing home's Prop 13 base-year value is preserved. In practice this typically adds $1,500–$4,000 per year in property tax depending on county and ADU value — usually less than one month of typical ADU rent.
How long does the permit process actually take?
State law caps city review at 60 days for a complete application, but plan-check rounds, corrections, and clearance from other agencies (school district, utilities) often add weeks. Plan for a realistic 8–18 weeks in most LA-area cities — slower in Pasadena and Santa Monica, faster if you use a pre-approved plan.
Can I do a garage conversion myself?
Legally, yes — homeowners can pull their own permits and self-perform work on their primary residence. Practically, plumbing and electrical inspections will catch unlicensed errors. Budget for at least a licensed electrician and a licensed plumber even if you're managing the project.
Do impact fees apply to my ADU?
ADUs under 750 sqft are exempt from school, park, and most other impact fees statewide. Over 750 sqft, you pay impact fees prorated on the difference (the fee scales with the marginal square footage, not the full ADU). This is the single most common reason ADUs are designed at 749 sqft.
Can I have more than one ADU on my property?
Single-family lots can have one ADU plus one Junior ADU (JADU, max 500 sqft, must be within the existing primary residence). Multifamily lots can have up to eight detached ADUs under SB 1211, capped at the number of existing primary units.
Will the bank lend on an ADU?
Yes — Fannie Mae and Freddie Mac both count projected ADU rental income toward mortgage qualification for refinances and purchase loans. CalHFA offers an ADU grant of up to $40,000 to cover pre-construction soft costs for eligible homeowners.
{# ----------------------------------------------------------------------------- IX. CTA — pre-set to this city ----------------------------------------------------------------------------- #}
SHEET 09 / 09 · Get matched

Get matched with three Long Beach builders who've done this before.

We hand-pick the contractors in Long Beach who actually permit and finish ADUs — not the ones with the loudest ads. No spam. No obligation.

Omar reads every submission by hand.

{# ----------------------------------------------------------------------------- X. SIBLINGS — other LA-area cities ----------------------------------------------------------------------------- #}
COLOPHON · Adjacent dossiers

Adjacent dossiers.

Compare Long Beach against neighboring cities — fees, timelines, and local rules vary more than state law might suggest.