A working cost estimator
What will your ADU actually cost?
Pick a city, an ADU type, a size, and a finish tier. We pull your city's real permit fee, multiply by current per-sqft build costs, layer on soft costs and contingency, and show you a defensible range — not a contractor's optimistic quote.
Estimate
Based on Detached new construction · 800 sqft · Standard finish in Los Angeles. Property uplift assumes a single-family lot baseline of $1M.
Line-by-line breakdown
- Build & finishes (360–$460/sqft × 800) $288k–$368k
- City permit & plan check $6.500
- Soft costs (design, survey, soils — 5–8% of build) $14k–$29k
- Utility connections (water, sewer, electrical) $8k–$14k
- Contingency (10% of subtotal) $31k–$41k
Drop your email to unlock the full breakdown.
See every line item — soft costs, contingency math, utility hookups. No spam. Omar reads every submission by hand.
How this is calculated.
-
01
Build cost band
We take the per-sqft cost range for your ADU type (detached / attached / garage conversion) from our 2026 LA-area cost survey, then apply a multiplier for the finish tier you picked (basic 0.85×, standard 1.00×, luxe 1.30–1.35×).
-
02
City permit fee
We add your selected city's typical permit + plan-check fee — pulled directly from each city's published fee schedule and verified May 2026. Impact fees (school, park) are handled separately because they depend on size threshold (the statewide 750 sqft exemption).
-
03
Soft costs & utilities
Design, survey, soils report, structural review: 5–8% of build. Utility connections (water, sewer, electrical separation): $8k–$14k. Both are conservative defaults — your project may be lower if you tie utilities into the primary residence.
-
04
Contingency
We add 10% of the subtotal as a contingency line. Don't skip this on a real project — change orders, site conditions, and price drift eat through it predictably.
-
05
Property value uplift
An ADU typically adds 25–35% to the appraised value of a single-family lot in LA-area markets, based on Fannie Mae appraisal guidance and recent comps. We show the dollar range against a $1M lot baseline — adjust mentally for your neighborhood.
What this estimator does not include: financing costs, landscaping, furniture, taxes during construction, or any second-mortgage points. Treat the band as your project envelope — not your bid.
Now find a builder who can deliver in your band.
We hand-pick three local builders who've actually permitted and finished ADUs at your size and finish tier. No spam. No obligation.